Since remobilising after the Christmas Shutdown the concrete works and service installation has progressed well, with much of the ILB ramp constructed as well as a good proportion of drainage, tanks and service ducts in and around the building slab installed. Preparation works for the ALB ramp continue, with filling and cutting down of the piles plus works to the gabions ready for the installation of the steelwork planned to commence from the 8th February. Concrete works will continue onto the sheet pile capping beam the rest of the month into early February; followed by the concrete works to the building slab.
Friday 26 Feb 2021
Concrete slab started, planks installed on ALB ramp
Saturday 20 Feb 2021
Steelwork completed for ALB ramp
Friday 12 Feb 2021
Winter weather and the ALB ramp
Friday 29 Jan 2021
Drainage and service ducts installed
22 Jan 2021
Works restart after Christmas
Sunday 20 Dec 2020
Ready for Christmas
Monday 30 Nov 2020
Piling almost done
Friday 20 Nov 2020
Installing piles for the main building
Monday 9 Nov 2020
Aerial site views
Sunday 1 Nov 2020
Sheet piling continues