New Boathouse Build

Wells' new boathouse from the ground up...

This gallery contains photographs of the site as it progresses. For more information and the latest updates, see our Boathouse Build pages.

Exit Gallery

 
Outline of office, plant room and loo on first floor
First floor looking towards office and plant room and stairs and lift up
Floor progress on gift shop and engagement space
Floor being laid in the cew changing area
New navigation marks - and the sea well up the new launching ramp - on a particularly high tide
First floor more complete
Gift shop and engagement space
Crew room floor looking south
Future view from the window of the crew room
First floor  for crew room and facilities going in
'Upstairs' looking at what will be the crew room, office, plant room and loo
Outside the south east corner of the building with the crew entrance (left) and workshop (right)
'Upstairs' looking north at what will be the crew room
Stud walls and plywood on the south eastern corner of the building
Plywood walls on the changing room and floor joists added above for the first floor crew room
Aerial view from south east
Aerial view from east
Aerial view from north
Aerial view from north
ILB shed with base of viewing platform and lifting beam on roof above
Stud walling going up around the crew changing facilities
Stud walling in place for the gift shop and engagement area
A start on the stud walling on the eastern side of the building
Boat hall with planked roof emerging from the scaffolding
Main roof looking seaward
Weatherproof membrane on tjhe main roof
Membrane installed on main roof
Craning planks onto the boathouse roof
Planking the main boat hall roof
Crew member (and station photographer) Ray West inspecting work on the roof!
Planking the main boat hall roof
Main roof being planked
Underside of roof from the shop area looking towards the inshore lifeboat shed
Scaffolding in the main boathall while the roof is constructed
Scaffolding being added for work on the roof
Timber roof in place over ILB shed and gift-shop/engagement space
Timber roof viewed from inside
Timber roof in place for ILB shed
Timber roof in place for ILB shed
New roof in place over gift shop and ILB shed
Interior roof for gift shop and ILB shed in place
Scaffolding erected on west side of building
Scaffolding on the west side of the building with frame for public viewing gallery visible on left
Scaffolding being erected on the west side of the building
View from the east
View from seaward
Suspended platform for public viewing gallery in place
Future entrance for engagement space and gift shop
Aerial view
Aerial view
Aerial view
Boat hall from the south
Almost complete frame
Almost completed frame
Boat hall roof beams being lifted into place
Remaining boat hall roof beams being lifted into place
Beams for the main roof of the boat hall going in
Crane operator
View from the south
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Adding metal support bars between the beams
View from along the beach bank
New and old viewed from the south east at low water
Constructing the frame
Constructing the frame
Constructing the frame
Craning the main boat hall roof beams into place
Constructing the frame
View from the south
Full moon rising
Partly completed frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Constructing the frame
Aerial view, restored historic lifeboat 'Lucy Lavers' on a trip round the harbour
Aerial view, current lifeboat station
Aerial view, new site and existing lifeboat station
Aerial view, new lifeboat station
Frame under construction
Frame under construction
Frame under construction, new beams delivered in the foreground
Beams being prepared to put into place
Frame on east side of building
Partly completed frame on eastern side of building
Lifeboat being recovered by the new boathouse after an exercise
Frame under construction
Quick progress lifting frame pieces into position in what will be the workshop area of the building
Beams being lifted and bolted into place
Start of the frame for the new boathouse... with the old boathouse behind
Quick progress on the first day of erecting the frame
First part of the frame for new boathouse frame being installed
First part of the frame for the new boathouse being lifted into place
First parts of the Glulam frame on-site ready to be installed
Inshore lifeboat briefly on the new all-weather lifeboat launching ramp during the 'Launch A Memory' opening
New crane setup on site for lifting the building frame
Beach reopened to the public and the new ramp already providing a sitting spot and some shade
Materials being delivered to site
Metal brackets in position for erecting the glulam frame
Pre-made and cut glulam beams delivered to site
Beams being prepared at Buckland Timber in Devon
Manufacture of the glulam beams at Buckland Timber in Devon
Manufacture of the glulam beams at Buckland Timber in Devon
Glulam beams being prepared at Buckland Timber in Devon
Beach bank path made good at the end of phase 1
ALB ramp finished at the end of phase 1
Side cleared at tjhe end of phase 1
South side filled. This area will eventuially be paved
South side filled. This area will eventuially be paved
Tidying up the site after filling the area to the south of the boathouse
Beach reopened around ALB ramp, scaffolding poles still acting as temporary navigation marks for boats
Filling  and levelling to the south of the new building
Site fencing rearranged around the site to reopen the beach
One of the last jobs for Mackley... levelling and filling the area to the south of the new boathouse
Lifeboat crew and Mackley construction crew on the newly built launching ramp
Completed ALB ramp with handrails added
Tidying up the site beyond to the north of the ILB ramp
Completed terracing
Connecting services to the site
ALB ramp with handrails
Levelled beach beyond the new lifeboat station
Finished terracing ready for planting
Timber facing and ILB ramp viewed from the beach
Connection to the existing beach bank made good
View down the ILB ramp
Base of the new building with what will be the crew changing area
Completed front apron and completed guard rail planking around the site and down the ILB ramp
Completed front apron looking east towards the ILB ramp and current boathouse
Drainage runs along the western edge of the building
Working on the front apron
Drilling rig being used for installation of the ground-sourced heat pump
Last sections of the front apron being built
Hand-digging a trench for the electricity supply to the station
Guard rail planking continuing round the eastern edge of the site
Working on the front apron
Beach dug out on the south side to make good the connection to the existing beach bank concrete slabs
Concrete path completed along the eastern side of the building
Installing more sections of the concrete apron in front of the building
Concrete apron almost complete, looking from the ALB ramp towards the building, ILB ramp on left
Progress with the guard rail
Washdown tank being installed
Ekki planks being installed to provide a guard rail around the site
Installing Ekki planks onto the capping beam to form a guard rail
Wash down tank being installed
More of the concrete front apron being constructed
Aerial site view
Aerial site view
Aerial site view
Aerial site view
Damp proof course and first rows of blocks installed
Installing damp proof course and first rows of blockwork around the building
Back filling the planked terraces around the perimeter of the site
Work starts on constructing the concrete apron between the building and the ALB ramp
First section of concrete apron between the building and the ALB ramp
Filling in the timber terraces on the eastern side of the site
Damp proof course and block work being installed
Outline of building starting to appear above the concrete slab
End closures on the timber planking around the site
Fill and compaction work to the north of the building
Upstands and damp proof course work on main building
South east side of site being filled and compacted
Work on upstands and damp proof course
Upstands on the main building slab
Filling around underground chambers
Upstand construction on the main slab
Grouting continues to ALB ramp with bolt and lifting holes filled
Timber planking around the edge of the site
Planking around the site continues
Concrete work at the top of the ALB ramp
Capping beam being completed between the ILB and ALB ramps
Finishing off the completed building slab
Finishing off the completed building slab
Finishing off the completed building slab
Completed building slab
Services installation
Concrete pouring for the building slab
Concrete pouring for the building slab
Service chambers being constructed south of the building
After last week's delay, the last major concrete pour is started
After last week's delay, the last major concrete pour is started
Shuttering and steel fixing in place ready for the concrete pour
Between the sheet piling and capping beam and the timber works
Capping beam progressing between the ILB ramp and the ALB ramp to the north
Capping beam progressing between the ILB ramp and the ALB ramp
Installing planking
Installing planking on the perimeter
The upper terrace of planking nearing completion
Adding planks to the timber piles around the perimeter of the site
Ready for concrete pour for the main slab... but bad weather means it has had to be postponed
Capping beam progressing between the ILB ramp and the ALB ramp to the north
Steelwork in place ready ahead of the main concrete pour
Rows of timber piles installed for the terracing around the perimeter of the site
Installing timber piles around the edge of the site
Reinforcing steel work in place on the building slab
Concrete poured on the south-west part of the building slab
Installing timber piles around the sheet-piled perimeter of the site
ALB ramp on the tide
Sheet piled perimeter and capping beam prior to timer terraces being installed
West side of site prepared for concrete pour
Beach being restored at foot of ALB ramp
Reinforcement steel in place ready for pouring more of the building slab
Sheet piling and capping beam at perimeter of site exposed ready for timber installation
Timber delivered for the terracing/breastwork around the sheet piled area
Fixing the concrete planks into position
Grouting the ALB ramp
Final precast concrete planks being installed at the foot of the ALB ramp
Foot of ALB ramp exposed again as final concrete planks are installed
Final precast concrete planks being installed at the foot of the ALB ramp
Concrete work progressing well on the west of the site
The new temporary footpath to the beach which will be in use shortly
The top of the ALB ramp with precast concrete planks in place
Concrete planks lifted onto and installed on ALB ramp
Concrete planks lifted onto and installed on ALB ramp
Concrete planks lifted onto and installed on ALB ramp
Lifting precast concrete planks into place on the ALB ramp
Tops of the tubular piles exposed on the western edge of the site as services are being installed
Shuttering and reinforcement steelwork being setup on the western side of the site
Precast concrete planks (made in Norfolk!) being moved to the beach ready for installation on the ALB ramp steelwork
Pouring concrete for the building slab
Pouring concrete for the building slab
Working on the building slab
Freshly poured concrete on the eastern side of the building slab
Pouring the first part of the the huge concrete slab on which the building will sit in the future area of the crew facilities and changing room
FIrst few concrete slabs for the surface of the ALB ramp delivered to site
East side of main site with shuttering and reinforcement steel ready for concrete slab to be poured
Hardcore and concrete work on the west side of the site catching up with progress on the east side
Reinforcing steel in place on the main site ready for concrete to be poured
ALB ramp with completed steelwork, the hole refilled and the tide back in
ALB ramp steelwork in place
Last pieces of steelwork going in
The last section of steelwork being installed at the base of the ALB ramp
Last pieces of steelwork going in
The last section of steelwork being installed at the base of the ALB ramp
Fastening the steelwork into place
Guiding the steelwork into place
Lifting the cross piece for the final set of piles into the hole
Digging out the base of the ALB ramp to install the final bay of steelwork
Steel in place on the main site ready for concrete building slab to be constructed
View from the top of the ALB ramp
Digging out the lower end of the ramp so steelwork can be installed on the piles
Steelwork in position on the ALB ramp
Work continues in the snow...
Bottom of ramp being dug out again ahead of steelwork being fitted
Steelwork being fitted inbetween snow showers
A frozen and snow covered site with work still on-going
Steel supports for the ALB ramp added to the piles
Craning ALB ramp steelwork into position
Pouring the capping beam
Pouring concrete for the capping beam towards the southern end of the building
Concrete capping beam leading from the ILB ramp
Hardcore and concrete layer being prepared on eastern side of the building
Completed ILB ramp with beach levelled off
Main site ready being readied for concrete pour
Compacting capping layers of hardcore on the main site
Last section of ILB ramp to go
Working on the ILB ramp and preparing the main site
The foot of the ILB ramp (this will be under the beach level when finished)
Finishing the top of the ILB ramp
Pouring concrete for the ILB ramp
Pouring concrete at the top of the ILB ramp
Service works on the main site
Cutting and filing works to the piles for the main ramp
Drainage and service works on the main site
Preparation work for the ILB ramp
Concrete poured for lower section of ILB ramp
Concreting the lower section of the ILB ramp
Concrete works for the ILB ramp
Concrete works for the ILB ramp
Concrete works for the ILB ramp
Drainage chambers being constructed
Capping beam being constructed around the sheet piles
Working on the capping beam at the southern edge of the site
A quiet site on New Year's Eve
A very cold dummy providing site security on New Year Eve
Christmas tree decorated by the crew after an exercise while the weather was still nice...
The ILB ramp waiting for concrete to be poured
Site tidied up and a Christmas tree added
The ALB ramp fenced off for the Christmas break
Preparing the ILB ramp for concreting
ILB ramp nearing completion
Preparing steelwork for the ILB ramp
Piles for main building and slab in place
Boathouse piles all in position
Finally the impact hammer drives the last pile in
The crane changing position on site, moving its own supporting mat piece by piece as it goes
The more powerful impact hammer being used to finish off stubborn piles
The more powerful impact hammer being used to finish off stubborn piles
Installing piles for the new building
Installing piles for the new building
Piling works
Vibro head suspended from the crane being used to drive piles in
Vibro head suspended from the crane being used to drive piles in
Installing piles for the new building
Installing piles for the main building
Installing piles for the new building
Installing piles for the new building
Piling starts on on the main site of the new building
More work on ILB ramp piling
View from the crane looking east towards existing boathouse
View from the crane northwards to sea
View from the crane - sheet piling around site
View from the crane looking south west over the beach bank
Sheet piling around the southern edge of the site
Sheet piling being added around the boathouse site
Sheet piling being added around the boathouse site
Top row of piles for the ALB ramp in position at the top of the bank
ILB ramp piling nearing completion
Sheet piling for the ILB ramp
Sheet piling the ILB ramp
Piling ready for boathouse foundations
Main site with start of sheet piling for ILB ramp
Driving in sheet piling for the ILB ramp
Beach piles in place and temporarily capped off
Piling for the ALB ramp
Piling for the ramp
Installing piles for the ALB ramp
Piling for the ALB ramp
Piling for the ramp
Piling for the ALB ramp
Quick progress with piling for the ramp
Adjusting the beach level during piling works for the ALB ramp
And onto the second...
First pile for the ramp being driven into the beach
First pile for the ramp being driven into the beach
First pile for the ramp being driven into the beach
Piling rig in place on the beach for piling with the crane passing the tubular steel piles over the sea defences
Main site, with steel piles ready for the ramp
Plant and materials ready for start of piling for the ramp to the north
Piling materials arriving on site
Normal service must go on: the lifeboat is recovered after an exercise on the beach to the east of the building site
Crane arriving on-site
Restored Liverpool-class lifeboat 'Lucy Lavers' passing the gap in the sea defences where the ALB ramp will be
The site ready for the arrival of the crane and piling equipment
Northerly gale
Northerly gale
Good progress on placing dredged fill material to bring site up to level in preparation for piling
Building up the beach level
View from the east with showing the raised beach level for the new boathouse
Scrub is cleared from the sea defences where the ramp for the Shannon lifeboat will be constructed
View from the east with the new beach level visible
Material dredged by Wells harbour from the channel is ferried back to the site across Wells beach
Raising the level of the site
The site is fenced off, plant has arrived and work started
Work begins on site... clearing the ground and base of the beach bank
Work begins on site... clearing the ground and base of the beach bank
Crew members and station officials, past and present, on the beach at the start of building work
Piling survey on the beach where the ALB ramp will come down from the new boathouse
A solitary stick marks the approximate south-east corner of the site where the new lifeboat station will be built
3D sketch plan
First floor plan
Ground floor plan
Artist's impression of new boathouse for Wells RNLI

Exit Gallery